Construction Claims and Variations

Expert-defined terms from the Postgraduate Certificate in Construction Law and Arbitration course at LearnUNI. Free to read, free to share, paired with a globally recognised certification pathway.

Construction Claims and Variations

Construction Claims and Variations Glossary #

Construction Claims and Variations Glossary

1 #

Acceleration

Accelerating a construction project refers to the process of completing the work… #

This may involve increasing resources, manpower, or working hours to meet deadlines.

2 #

Adjudication

Adjudication is a dispute resolution process commonly used in construction contr… #

It involves appointing a neutral third party, known as an adjudicator, to make a binding decision on a dispute between parties.

3 #

Arbitration

Arbitration is a formal dispute resolution method where parties present their ca… #

It is often used in construction contracts as an alternative to litigation.

4 #

Change Order

A change order, also known as a variation order, is a written amendment to the c… #

It is used to document any changes made during the course of the project.

5 #

Claim

In construction, a claim is a demand by one party for compensation or relief due… #

Claims can arise from various sources, including changes in scope, delays, or unforeseen circumstances.

6 #

Concurrent Delay

Concurrent delay occurs when two or more delay events happen at the same time, i… #

It can complicate delay analysis and apportioning responsibility for the delays between parties.

7 #

Constructive Acceleration

Constructive acceleration happens when a contractor is entitled to an extension… #

The contractor may be entitled to additional compensation for the acceleration.

8 #

Counterclaim

A counterclaim is a claim made by the defendant in response to the claimant's in… #

In construction disputes, parties may file counterclaims to seek compensation or other remedies against the claimant.

9 #

Delay Damages

Delay damages, also known as liquidated damages, are predetermined amounts of mo… #

These damages are typically specified in the construction contract.

10 #

Disruption

Disruption in construction refers to any event that causes inefficiencies, hindr… #

It can lead to increased costs, delays, and disputes between parties.

11 #

EOT (Extension of Time)

An extension of time (EOT) is a formal adjustment to the project schedule to acc… #

EOTs allow contractors additional time to complete the work without facing penalties for late completion.

12 #

FIDIC (International Federation of Consulting Engineers)

The FIDIC is a globally recognized organization that produces standard forms of… #

FIDIC contracts are widely used in international construction projects and provide a framework for managing risks and disputes.

13 #

Force Majeure

Force majeure refers to unforeseeable events or circumstances that are beyond th… #

Force majeure clauses in contracts may excuse parties from liability in such situations.

14 #

Liquidated Damages

Liquidated damages are predetermined amounts of money specified in the contract… #

These damages serve as compensation for the non-breaching party.

15 #

Mediation

Mediation is a voluntary and informal dispute resolution process where a neutral… #

It is often used in construction disputes to facilitate communication and negotiation.

16 #

Notice of Claim

A notice of claim is a formal written communication sent by one party to another… #

It is a crucial document in construction contracts as it triggers the contractual mechanisms for resolving disputes.

17 #

Omission

An omission in construction refers to work that was originally included in the c… #

Omissions may arise due to design changes, cost-saving measures, or other reasons and can impact the project's scope and cost.

18 #

Quantum Meruit

19 #

Retention

Retention is a common practice in construction contracts where a specified perce… #

Retention is usually released upon completion of the project.

20 #

Termination for Convenience

Termination for convenience allows one party to end the contract without breachi… #

This clause is often included in construction contracts to provide flexibility in terminating the agreement.

21 #

Variation

A variation, also known as a change order, is a modification to the original sco… #

Variations can be initiated by either party and must be documented in writing to avoid disputes.

22 #

Withholding Notice

A withholding notice is a formal communication from one party to another indicat… #

It serves as a warning before further actions are taken.

23. Zero #

Cost Variation

A zero #

cost variation occurs when a change in the scope of work does not result in any additional cost to the contractor. Zero-cost variations are often minor changes that can be accommodated within the original contract sum without affecting the overall project budget.

May 2026 cohort · 29 days left
from £90 GBP
Enrol